Construction progress of HYGGE - February 2021 - LEV

Construction progress of HYGGE – February 2021

March 2021
01

In February 2021:

  • facade works in section III continued, insert 2-3;
  • the inner walls 1-2 in section III were plastered;
  • railings and railings of balconies of the III section are installed;
  • completed the installation of waterproofing on the terraces of commerce;
  • arranged cable trays for power supply in the parking lot and all sections;
  • mounted aluminum facade structures in commerce;
  • completed the installation of window and balcony outflows in sections II-III;
  • the filling of screeds in sections I and II continued;
  • performed monolithic works, filled the floor slab over the parking lot;
  • completed the installation of plumbing in section III on the 5th-7th floor.