In February 2021:
- 40% of the walls and partitions on the 4th floor were bricked up;
- walls and partitions on the 5th and 6th floors were bricked up by 20%;
- completed the installation of ventilation ducts;
- 50% of monolithic works on the entrance to the 2nd level of the parking lot have been completed.