In August 2020:
- Work on the installation of the floor slab above the 7th floor has been completed;
- Stairs are arranged from the 6th to the 7th floor;
- Work on concreting parapets continues;
- Arrangement of the formwork of stairways from the 6th to the 7th floor;
- Works on concreting of vertical elements of the 7th floor are completed;
- Completed work on concreting the floor slab above the 6th floor;
- Completed the arrangement of stairways from 6 to 7 floors.