In August 2020:
- Completed the masonry of the interior walls in the 3rd section on the 1st, 3rd, 5th, 6th floor;
- Ventilation systems were installed (insert 2-3 on the 1st, 2nd, 3rd floor);
- Work on plumbing continued in the 2nd section;
- Facade works in the 1st and 2nd sections continued;
- Executed electricity, in -2 levels of parking of the 2nd section;
- Arranged external sewerage;
- Completed all plastering works in the 2nd section;
- Performed installation of electricity in -2 levels of parking of the 2nd section;
- Arranged insulation of terraces with extruded foam.