Construction progress of HYGGE 148 - August 2020 - LEV

Construction progress of HYGGE 148 – August 2020

September 2020
04

In August 2020:

  • Completed the masonry of the interior walls in the 3rd section on the 1st, 3rd, 5th, 6th floor;
  • Ventilation systems were installed (insert 2-3 on the 1st, 2nd, 3rd floor);
  • Work on plumbing continued in the 2nd section;
  • Facade works in the 1st and 2nd sections continued;
  • Executed electricity, in -2 levels of parking of the 2nd section;
  • Arranged external sewerage;
  • Completed all plastering works in the 2nd section;
  • Performed installation of electricity in -2 levels of parking of the 2nd section;
  • Arranged insulation of terraces with extruded foam.