Construction progress of OBRIY 3 - August 2020 - LEV

Construction progress of OBRIY 3 – August 2020

September 2020
03

In August 2020:

  • Piles were drilled and the foundation slab of the 4th section was concreted;
  • Concreted walls and columns -2 level of the parking lot of the 4th section;
  • Concrete walls and columns of commerce of the 2nd section were concreted;
  • Concreted the floor of the 1st residential floor of the 2nd section;
  • 50% of the waterproofing of the walls and foundation was performed in the 3rd and 4th sections;
  • Insulated and poured screed on the roof of the 1st section;
  • Completed the installation of ventilation ducts in the 1st section;
  • The external walls on the 9th floor and on the technical floor in the 1st section continued to be bricked up;
  • Partitions on the 7th, 8th, and 9th floors in the 1st section continued to be built.
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT