In August 2020:
- Piles were drilled and the foundation slab of the 4th section was concreted;
- Concreted walls and columns -2 level of the parking lot of the 4th section;
- Concrete walls and columns of commerce of the 2nd section were concreted;
- Concreted the floor of the 1st residential floor of the 2nd section;
- 50% of the waterproofing of the walls and foundation was performed in the 3rd and 4th sections;
- Insulated and poured screed on the roof of the 1st section;
- Completed the installation of ventilation ducts in the 1st section;
- The external walls on the 9th floor and on the technical floor in the 1st section continued to be bricked up;
- Partitions on the 7th, 8th, and 9th floors in the 1st section continued to be built.