Construction progress of OBRIY 2 - August 2020 - LEV

Construction progress of OBRIY 2 – August 2020

September 2020
02

In August 2020:

  • Completed the installation of tiles in the 2nd and 95% completed the installation in the 3rd section;
  • Completed the installation of putty of the 3rd section and at the finish in the 2nd;
  • Painted walls on the 5th, 6th, 7th floor in the 1st section;
  • 70% of the installation of lightning protection was performed in 1, 2, 3 sections;
  • Completed the installation of entrance doors 1, 2, 3 sections;
  • Completed the installation of handrails on the balconies of 1, 2, 3 sections by 95%;
  • Arranged fire sensors in the parking lot of sections 1, 2, 3.