In August 2020:
- Completed the installation of tiles in the 2nd and 95% completed the installation in the 3rd section;
- Completed the installation of putty of the 3rd section and at the finish in the 2nd;
- Painted walls on the 5th, 6th, 7th floor in the 1st section;
- 70% of the installation of lightning protection was performed in 1, 2, 3 sections;
- Completed the installation of entrance doors 1, 2, 3 sections;
- Completed the installation of handrails on the balconies of 1, 2, 3 sections by 95%;
- Arranged fire sensors in the parking lot of sections 1, 2, 3.