Construction progress of LEV CITY HOTEL - August 2021 - LEV Development

Construction progress of LEV CITY HOTEL – August 2021

September 2021
02

At the end of August 2021:

  • Installation of plasterboard ceilings on 3-5 floors proceeds;
  • Installation of elevators is completed;
  • Installation of the power supply system continues;
  • Installation of the ventilated facade proceeds;
  • Installation of ventilating air ducts continues;
  • The pouring of the cement-sand screed on the 4th floor was completed and continued on the 5th floor.
/