At the end of August 2021:
- Installation of plasterboard ceilings on 3-5 floors proceeds;
- Installation of elevators is completed;
- Installation of the power supply system continues;
- Installation of the ventilated facade proceeds;
- Installation of ventilating air ducts continues;
- The pouring of the cement-sand screed on the 4th floor was completed and continued on the 5th floor.
/