At the end of August 2021:
- 100% of vertical structures of the 4th floor (walls, pylons) of the I section are concreted;
- 50% of masonry of external and internal walls of the 1st floor of the I section is executed;
- 100% of vertical structures (pylons, walls) of the 8th floor of the II section are concreted;
- The floor slab of the 8th floor of the II section is concreted;
- 50% of masonry of external and internal walls of the 3rd floor of the II section is executed;
/