Construction progress of LEV CITY HOTEL – May 2021

June 2021
02

In May 2021:

  • Finished plastering the walls on the 2nd floor and started plastering on the 4th floor;
  • Installation of the power supply system of the rooms continued;
  • Installation of aluminum windows on stairwells continued;
  • The masonry of the walls and partitions of the 1st floor continued;
  • Installation of faucets in bathrooms continued.
/