In May 2021:
- Finished plastering the walls on the 2nd floor and started plastering on the 4th floor;
- Installation of the power supply system of the rooms continued;
- Installation of aluminum windows on stairwells continued;
- The masonry of the walls and partitions of the 1st floor continued;
- Installation of faucets in bathrooms continued.
/