In May 2021:
- Completed the floor of the 2nd floor of Section II;
- Concreting of vertical structures (walls, pylons) of the 3rd floor in the II section is performed;
- Completed the pile field in Section I;
- Preparations for the installation of the foundation slab in Section I have begun.
/