Construction progress of OBRIY 3 - May 2021 - LEV Development

Construction progress of OBRIY 3 – May 2021

June 2021
02

In May 2021:

  • Completed the installation of window structures of sections II and III;
  • Completed the installation of the first layer of roof waterproofing in sections II, III, IV;
  • Completed plastering works on the 4th, 5th, 6th, 7th floors of the I section;
  • Heating radiators were installed on the 2nd, 3rd, and 4th floors of Section I;
  • Floor screeds were poured on the 2nd and 3rd floors of the I section;
  • Completed masonry of walls and partitions in II, III, IV sections;
  • Conducted input electrical and Internet cables to the apartments of II and III sections;
  • Completed 60% of facade works in the I section.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію