In May 2021:
- Completed the installation of window structures of sections II and III;
- Completed the installation of the first layer of roof waterproofing in sections II, III, IV;
- Completed plastering works on the 4th, 5th, 6th, 7th floors of the I section;
- Heating radiators were installed on the 2nd, 3rd, and 4th floors of Section I;
- Floor screeds were poured on the 2nd and 3rd floors of the I section;
- Completed masonry of walls and partitions in II, III, IV sections;
- Conducted input electrical and Internet cables to the apartments of II and III sections;
- Completed 60% of facade works in the I section.
/