Хід будівництва ЖК ARTHOUSE park - Construction progress of RC ARTHOUSE park - - Май 2021[:] - LEV Development

Construction progress of RC ARTHOUSE park – May 2021

June 2021
01

In May 2021:

In section III:

  • The concreting of the floor slab from the 4th to the 7th floors has been completed;
  • Concreting of vertical structures on the 5th, 6th, 7th floors was completed;
  • The masonry of the outer walls on the 1st, 2nd, and 3rd floors began;
  • The laying of internal partitions on the 1st floor began.

In section I:

  • Completed concreting -1 level of parking;
  • The concreting of vertical structures and commercial floor slabs has been completed;
  • Concreting of vertical structures of the 1st and 2nd floors was completed;
  • Completed concreting of the floor slab above the 1st floor;
  • The installation of the floor slab formwork above the 2nd floor is in progress.
/