In May 2021:
In section III:
- The concreting of the floor slab from the 4th to the 7th floors has been completed;
- Concreting of vertical structures on the 5th, 6th, 7th floors was completed;
- The masonry of the outer walls on the 1st, 2nd, and 3rd floors began;
- The laying of internal partitions on the 1st floor began.
In section I:
- Completed concreting -1 level of parking;
- The concreting of vertical structures and commercial floor slabs has been completed;
- Concreting of vertical structures of the 1st and 2nd floors was completed;
- Completed concreting of the floor slab above the 1st floor;
- The installation of the floor slab formwork above the 2nd floor is in progress.
/