Construction progress of LIFE STORY - July 2021 - LEV Development

Construction progress of LIFE STORY – July 2021

August 2021
05

At the end of July 2021:

  • The floor of the 1st floor of the I section has been completed;
  • 80% of vertical structures (pylons, walls) of the second floor of the I section are concreted;
  • 100% of vertical structures (pylons, walls) of the 6th floor of the II section are concreted;
  • The floor of the 7th floor of Section II has been completed;
  • 50% of ventilation units of the 4th floor of the II section are installed;
  • 55% of the masonry of the 2nd floor of the external and internal walls of the II section was made.
/