Construction progress of OBRIY 3 - July 2021 - LEV Development

Construction progress of OBRIY 3 – July 2021

August 2021
02

In July 2021:

  • Finished pouring screeds in section I;
  • 80% of screeds were filled in section II;
  • Finished plastering the walls in section II;
  • Plastering works have started in Section III;
  • The installation of the heating system in Section II was completed.
/