At the end of September 2021:
Section I
- 100% of vertical structures (pylons, walls) of the 6th floor are concreted;
- 55% of masonry of external and internal walls of the 2nd floor is executed;
- 35% of masonry of external and internal walls of the 3rd floor is executed;
Section II
- 50% of vertical structures (pylons, walls) of the 11th floor are concreted;
- 45% masonry of the 4th floor of external and internal walls is made;
- 40% of the masonry of the 1st floor of the external and internal walls was made;
- 50% of ventilation ducts are installed on the 8th floor.
/