Construction progress of LIFE STORY - September 2021 - LEV Development

Construction progress of LIFE STORY – September 2021

October 2021
05

At the end of September 2021:

Section I

  • 100% of vertical structures (pylons, walls) of the 6th floor are concreted;
  • 55% of masonry of external and internal walls of the 2nd floor is executed;
  • 35% of masonry of external and internal walls of the 3rd floor is executed;

Section II

  • 50% of vertical structures (pylons, walls) of the 11th floor are concreted;
  • 45% masonry of the 4th floor of external and internal walls is made;
  • 40% of the masonry of the 1st floor of the external and internal walls was made;
  • 50% of ventilation ducts are installed on the 8th floor.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію