At the end of September 2021:
- Work continued on the installation of plasterboard ceilings on 3-5 floors;
- Work on plastering the walls on 3-4 floors continued;
- Work continued on plastering the walls on the 1st floor;
- Work continued on the arrangement of the power supply system;
- Work continued on the installation of a ventilated facade;
- Work on the installation of cement-sand screed on 5-7 floors has been completed;
- Works on installation of ventilating air ducts are completed;
- The installation of the air conditioning system continued;
- The installation of the floor heating system on the ground floor continued.
/