Construction progress of LEV CITY HOTEL - September 2021 - LEV Development

Construction progress of LEV CITY HOTEL – September 2021

October 2021
05

At the end of September 2021:

  • Work continued on the installation of plasterboard ceilings on 3-5 floors;
  • Work on plastering the walls on 3-4 floors continued;
  • Work continued on plastering the walls on the 1st floor;
  • Work continued on the arrangement of the power supply system;
  • Work continued on the installation of a ventilated facade;
  • Work on the installation of cement-sand screed on 5-7 floors has been completed;
  • Works on installation of ventilating air ducts are completed;
  • The installation of the air conditioning system continued;
  • The installation of the floor heating system on the ground floor continued.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію