Construction progress of RC ARTHOUSE park – JUNE 2023

July 2023
05

In June 2023:

  • A technical door was installed in the house;
  • Land improvement works have been completed;
  • A gate to the parking lot has been installed;
  • Painting of sections I and II has begun;
  • The laying of fire extinguishing networks has been completed;
  • Ceramic wall tiles have been installed on executive floors;
  • Measurements have been taken and work is ongoing on the manufacture of stairwell fencing;
  • Landscaping of the surrounding area has been completed;
  • External lighting is installed.
/