In June 2023:
- Section IV:
- Completed works on the arrangement of the water supply system and the heating system;
- Batteries have been installed;
- A sewage system has been installed.
- Section V:
- The flooring of the 1st floor is finished;
- The laying of the wall of the 2nd floor has been completed;
- Work is being carried out on the arrangement of the ceiling of the 2nd floor.
- Section VI:
- The foundation slab is completely arranged;
- The construction of the wall of the second floor is completed;
- The construction of the floor – 2nd floor has been completed;
- Work is being carried out on the arrangement of the walls of the 1st floor.