Construction progress of RC ARTHOUSE park - April 2021 - LEV Development

Construction progress of RC ARTHOUSE park – April 2021

May 2021
05

In April 2021:

  • Concrete slab of the 2nd floor of the III section;
  • 80% of the backfill of the pit of the III section was performed;
  • The floor slab of the 3rd floor and the vertical structures of the 4th floor in the III section were concreted;
  • Completed the development of the pit of section I;
  • The concreting of the foundation slab of the first section was completed;
  • Completed concreting of vertical structures of the parking lot of the 2nd floor of the first section;
  • Arranged a floor slab over the parking lot of the 2nd floor of the first section;
  • Arranged floor slab of the 4th floor of the III section;
  • Vertical structures of the 5th floor of the III section were concreted;
  • Reinforcement of the floor slab above the 5th floor of the III section was continued.
/