In April 2021:
- Concrete slab of the 2nd floor of the III section;
- 80% of the backfill of the pit of the III section was performed;
- The floor slab of the 3rd floor and the vertical structures of the 4th floor in the III section were concreted;
- Completed the development of the pit of section I;
- The concreting of the foundation slab of the first section was completed;
- Completed concreting of vertical structures of the parking lot of the 2nd floor of the first section;
- Arranged a floor slab over the parking lot of the 2nd floor of the first section;
- Arranged floor slab of the 4th floor of the III section;
- Vertical structures of the 5th floor of the III section were concreted;
- Reinforcement of the floor slab above the 5th floor of the III section was continued.
/