Construction progress of OBRIY 3 - April 2021 - LEV Development

Construction progress of OBRIY 3 – April 2021

May 2021
05

In April 2021:

  • Completed the installation of the second layer of roofing material on the roof of the first section;
  • Completed the installation of window structures and sections;
  • Completed plastering works of 2-4 floors of the I section;
  • Installation of the heating system of the I section has begun;
  • 40% of facade works in the first section were performed;
  • Completed the installation of the ventilation system;
  • Completed the installation of a collective smoke extraction system (SKD);
  • The masonry of walls and partitions of 5-6 floors was completed;
  • Completed the installation of a sloping screed on the roof;
  • Work has begun on the installation of roof waterproofing;
  • Installation of window constructions of the II section has begun.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію