Construction progress of RC ARTHOUSE park - November 2021 - LEV Development

Construction progress of RC ARTHOUSE park – November 2021

November 2021
29

In November 2021:

  • The masonry of the external and internal walls of the I section was completed;
  • Installation of electric lighting networks in public places of the I section has begun;
  • Completed the masonry of the outer walls by 90% mounted ventilation of the apartments of section II;
  • 80% of the sewerage pipelines of section III are installed;
  • The masonry of the external walls of Section III has been completed;
  • Masonry of internal partitions on 12-14 floors of the III section is completed;
  • The masonry of the internal partitions on the 11th floor of Section III continued;
  • 95% of ventilation systems of section III are installed.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT
запис на консультацію