In November 2021:
- The masonry of the external and internal walls of the I section was completed;
- Installation of electric lighting networks in public places of the I section has begun;
- Completed the masonry of the outer walls by 90% mounted ventilation of the apartments of section II;
- 80% of the sewerage pipelines of section III are installed;
- The masonry of the external walls of Section III has been completed;
- Masonry of internal partitions on 12-14 floors of the III section is completed;
- The masonry of the internal partitions on the 11th floor of Section III continued;
- 95% of ventilation systems of section III are installed.
/