In November 2021:
- Concrete works of 2-4 floors of the I section were completed;
- Bricklaying of the 1st floor of the I section began;
- Concrete works of 1-2 floors of I and II sections were completed;
- Concrete works of the 3rd floor of the I and II sections have begun;
- The concrete works of the parking lot of the IV section have been completed;
- Concrete works of the 1st floor of the IV section have begun
/