In February 2023:
- The installation of heating and water supply systems for apartments on the 2nd and 3rd floors of the III section has been completed;
- Installation of heating systems on the 1st floor has begun;
- Installation of the sand-cement screed on the 2nd floor of the III section has begun;
- The installation of electric accounting cabinets in all sections has been completed and the laying of external power supply networks has been completed;
- Work has begun on the installation of balcony fences of the III section.