PERFECT LIFE CONSTRUCTION PROGRESS - February 2023[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – February 2023

March 2023
03

In February 2023:

  • Completed masonry of the external walls of the 2nd-8th floors of the 1st section;
  • Masonry of the internal walls and partitions of the 2-3 floors of the 1st section began;
  • They arranged a foundation slab for the school of the 1st section;
  • Ventilation risers of the 2nd to 8th floors of the 1st section were installed;
  • The columns and walls of the 2nd floor of the II section were installed;
  • A floor slab was installed above the 2nd floor of the II section;
  • Monolithic columns and walls of the 3rd floor of the II section were installed;
  • The foundation plate of the III section was laid;
  • Work has begun on the arrangement of the monolithic walls of the parking lot of the III section.
/