In February 2023:
- Completed masonry of the external walls of the 2nd-8th floors of the 1st section;
- Masonry of the internal walls and partitions of the 2-3 floors of the 1st section began;
- They arranged a foundation slab for the school of the 1st section;
- Ventilation risers of the 2nd to 8th floors of the 1st section were installed;
- The columns and walls of the 2nd floor of the II section were installed;
- A floor slab was installed above the 2nd floor of the II section;
- Monolithic columns and walls of the 3rd floor of the II section were installed;
- The foundation plate of the III section was laid;
- Work has begun on the arrangement of the monolithic walls of the parking lot of the III section.