In January 2022:
- Installation of window constructions on 1-9 floors of the I section is completed;
- Masonry of chimneys of the I section is completed;
- 80% of the collective smoke removal system of Section III has been installed;
- Installation of window constructions on the 11-14th floor of the III section continues;
- The masonry of the internal partitions of Section III has been completed;
- The masonry of the walls at the -1 level of the parking lot of the III section has been completed.
/