At the end of January 2022:
Section 1
- The floor of the 13th floor has been completed;
- 50% of vertical structures of the 14th floor (walls, pylons) were concreted.
Section 2
- 80% of vertical roof structures (parapets) are concreted;
- 100% of ventilation ducts of the 14th floor were installed;
- 10% of masonry of 10 and 11 floors of external walls was made.
/