Construction progress of LIFE STORY - January 2022 - LEV Development

Construction progress of LIFE STORY – January 2022

February 2022
07

At the end of January 2022:

Section 1

  • The floor of the 13th floor has been completed;
  • 50% of vertical structures of the 14th floor (walls, pylons) were concreted.

Section 2

  • 80% of vertical roof structures (parapets) are concreted;
  • 100% of ventilation ducts of the 14th floor were installed;
  • 10% of masonry of 10 and 11 floors of external walls was made.
/