In September 2021:
- The masonry of the external walls in Section I was completed;
- Completed masonry of internal partitions on 3-5 floors;
- Arranged insulation of the coating in section I;
- The waterproofing of a covering of the I section is arranged;
- The masonry of the external walls on the 9th-11th floors in Section III was completed;
- The masonry of the external walls on the 10th-13th floor of Section III continued;
- The masonry of the internal partitions on the 8th-10th floor of Section III continued;
- All monolithic works in sections II and III have been completed;
- Installation of ventilation ducts on 8-10 floors of 3 sections and on 6-8 floors of I section continues.
/