Construction progress of RC ARTHOUSE park – September 2021

October 2021
07

In September 2021:

  • The masonry of the external walls in Section I was completed;
  • Completed masonry of internal partitions on 3-5 floors;
  • Arranged insulation of the coating in section I;
  • The waterproofing of a covering of the I section is arranged;
  • The masonry of the external walls on the 9th-11th floors in Section III was completed;
  • The masonry of the external walls on the 10th-13th floor of Section III continued;
  • The masonry of the internal partitions on the 8th-10th floor of Section III continued;
  • All monolithic works in sections II and III have been completed;
  • Installation of ventilation ducts on 8-10 floors of 3 sections and on 6-8 floors of I section continues.
/