Construction progress of RC ARTHOUSE park – September 2022

October 2022
05

In September 2022:

  • Installation of aluminum window structures in sections I and III continued;
  • Installation of the water supply system in the III section continued;
  • The plastering of the walls in the apartments in the III section was completed;
  • 90% of parapets have been installed in the III section;
  • The plastering of the walls in the apartments in the III section was completed;
  • The installation of roofs over the chimneys in the III section has been completed.
/