In September 2022:
- Masonry of the partitions of the 5th floor of the 1st section has been completed;
- Lining of roof chimneys with metal sheets and installation of gutters for drainage has begun;
- Masonry of the ventilation ducts and chimneys of the 6th floor of the II section has been completed;
- The installation of the wooden structures of the roof of the II section has begun;
- Concreting of the stairs from the 5th to the 6th floor of the II section was completed;
- Masonry of the pediments and parapets of the 6th floor of the III section has been completed;
- The installation of metal channels under the structure of the roof of the III section was carried out;
- Concreting of the stairs from the 5th to the 6th floor of the III section was completed;
- Concreting of the parapets of the 6th floor of the III section was completed;
- Installation of ventilation and chimney units on the 4th floor of the III section was completed;
- Masonry of the gables of the 6th floor of the IV section was completed;
- The parapets of the 6th floor of the IV section have been concreting.