Construction progress of the Central Hills – July 2026

July 2026
23

Construction progress of the CENTRAL HILLS as of July 2026:

At Slate Tower:

  • Monolithic works are underway at the 18th floor level;
  • Concrete was adopted for the construction of a monolithic frame.

At Ruby Tower:

  • Window installation is underway — double-glazed windows have been installed from the 2nd to the 25th floors;
  • The interior walls on the 26th floor are being laid;
  • External and internal walls and partitions are made from the 2nd to the 25th floor.
/