Progress of construction of the LIFE STORY as of July 2026:
- Work is underway to concretize the vertical walls and columns of the parking lot located between the 1st and 2nd sections.
- Tile installation is underway on the 2nd floor of the 1st section.
- Freight elevators are being installed.