Actual news for July from the FEEL HOUSE residential complex construction site in Lviv:
In the I section:
- Water meters have been installed;
- Installation of sewage pipes is completed.
In II-III sections:
- Water meters have been installed;
- Installation of sewage pipes is completed.
In the IV section:
- Plumbing works on the 5th floor have been completed;
- An elevator is installed;
- The installation of the screed is completed.
Overall for the house:
- Monolithic works on the arrangement of the attached parking lot are in progress;
- Construction of the road has been completed;
- The installation of gas pipes has begun.