Хід будівництва ЖК FEEL HOUSE - Construction progress of FEEL HOUSE - - Январь 2022[:] - LEV Development (Лев Девелопмент)

Construction progress of FEEL HOUSE – JULY 2023

August 2023
01

Actual news for July from the FEEL HOUSE residential complex construction site in Lviv:

In the I section:

  • Water meters have been installed;
  • Installation of sewage pipes is completed.

In II-III sections:

  • Water meters have been installed;
  • Installation of sewage pipes is completed.

In the IV section:

  • Plumbing works on the 5th floor have been completed;
  • An elevator is installed;
  • The installation of the screed is completed.

 

Overall for the house:

  • Monolithic works on the arrangement of the attached parking lot are in progress;
  • Construction of the road has been completed;
  • The installation of gas pipes has begun.
/