In July 2023:
- In the I section:
- Work on warming the facades has begun;
- Works on laying pipes of the heating and water supply system of 4-5 floors are being carried out;
- Electrical networks are being laid in apartments on 7-8 floors;
- Low-current networks (Internet, intercom) are being laid on 6-8 floors.
- In II, III, IV sections:
- The masonry of the outer walls of the 2-5 floors has begun;
- Reinforcement of the foundation slab of the parking lot has begun.
- In V, VI sections:
- Arrangement of columns and walls of the 1st floor;
- The formwork of the floor slab above the 1st floor has begun.