PERFECT LIFE CONSTRUCTION PROGRESS - JULY 2023[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – JULY 2023

August 2023
03

In July 2023:

  • In the I section:
    • Work on warming the facades has begun;
    • Works on laying pipes of the heating and water supply system of 4-5 floors are being carried out;
    • Electrical networks are being laid in apartments on 7-8 floors;
    • Low-current networks (Internet, intercom) are being laid on 6-8 floors.

 

  • In II, III, IV sections:
    • The masonry of the outer walls of the 2-5 floors has begun;
    • Reinforcement of the foundation slab of the parking lot has begun.

 

  • In V, VI sections:
    • Arrangement of columns and walls of the 1st floor;
    • The formwork of the floor slab above the 1st floor has begun.
/