In July 2023:
House 1:
- Masonry of interior partitions on the 2nd and 3rd floors has begun;
- Work has begun on the insulation of the facade;
- Work has begun on the arrangement of the foundations of the parking lots between the first and second buildings.
House 2:
- Installation of ventilation systems has been completed;
- Preparations for roof insulation have begun;
- Masonry of the internal walls has begun.
House 3:
- Finished concrete works on the arrangement: floor slabs of the 4th floor; walls and columns of the 5th floor;
- Masonry of the external walls of the 1st floor is underway.
House 4:
- The ceiling of the 2nd floor and the walls and columns of the 1st floor are poured.