SILENT PARK CONSTRUCTION PROGRESS - JULY 2023[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – JULY 2023

August 2023
03

In July 2023:

House 1:

  • Masonry of interior partitions on the 2nd and 3rd floors has begun;
  • Work has begun on the insulation of the facade;
  • Work has begun on the arrangement of the foundations of the parking lots between the first and second buildings.

House 2:

  • Installation of ventilation systems has been completed;
  • Preparations for roof insulation have begun;
  • Masonry of the internal walls has begun.

House 3:

  • Finished concrete works on the arrangement: floor slabs of the 4th floor; walls and columns of the 5th floor;
  • Masonry of the external walls of the 1st floor is underway.

House 4:

  • The ceiling of the 2nd floor and the walls and columns of the 1st floor are poured.
/