In July 2023:
- Section IV:
- Completed plastering of common corridors and staircases.
- Section V:
- The covering of the 2nd floor is finished;
- The laying of the wall of the 3rd floor has been completed;
- Work is being carried out on the arrangement of the ceiling of the 3rd floor.
- Section VI:
- The laying of the wall of the 1st floor has been completed;
- The construction of the floor -1 floor has been completed;
- The arrangement of the walls of the 1st floor has been completed.