Current news for November from the FEEL HOUSE residential complex construction site in Lviv:
In the I section:
- Plastering of the corridor on the 1st and 2nd floors was completed;
- Installation of windows is completed;
- Facade work has begun;
- The installation of the electric cable for lighting the stairwell from the 1st to the 5th floor has been completed.
In II-III sections:
- Masonry of the partitions of the 5th floor is finished;
- The installation of the electric cable for lighting the stairwell from the 1st to the 5th floor has been completed.
In the IV section:
- Masonry of the parapets and walls of the 6th floor was completed;
- Masonry of the partitions of the 1st, 2nd, and 5th floors was completed;
- Masonry of the partitions of the 3rd and 4th floors has begun;
- Masonry of the ventilation ducts and chimneys of the 6th floor has begun;
- The installation of ventilation units and chimneys on the 4th and 5th floors has been completed;
- Sewer risers have been installed.