In November 2022:
In the I section:
- The installation of the cement-sand screed on the 2nd-9th floor has been completed;
- The installation of window moldings has been completed.
In the III section:
- The installation of the cement-sand screed on the 9th-14th floors has been completed;
- The concreting of the entrance to the -2nd level of the parking lot continued;
- Installation of heating and water supply systems in apartments on the 6th floor continued.