Construction progress of FEEL HOUSE – NOVEMBER 2023

December 2023
02

Current news for November from the FEEL HOUSE residential complex construction site in Lviv:

  • Boilers of II-IV sections have been installed;
  • Mounted canopies of entrance doors of sections II-IV;
  • Painting works on the 1st-5th floors of the 4th section have been completed;
  • Installation of ceramic tiles on the 3rd floor of the 4th section has been completed;
  • Installation of ceramic tiles on the 4th floor of the 4th section has begun.
  • Installation of a PVC membrane in the courtyard has begun;
  • A concrete road has been laid and improvement works are ongoing.
/