In November 2023:
- Section IV:
- Work was carried out on the installation of facade insulation.
- Section IV:
- The columns of the 1st floor of commerce are 100% filled;
- Work is underway to arrange the ceiling of the 1st floor of commerce.
- Section V:
- The columns of the 4th floor are fully arranged;
- The ceiling of the 4th floor is 100% filled
- The columns of the 5th floor are fully arranged;
- 100% coverage of the 5th floor.
- Section VI:
- The ceiling of the 6th floor is 100% filled;
- The columns of the 7th floor are fully arranged;
- The overlap of the 7th is filled with 100%;
- Bricklaying of the walls of the 1st residential floor has begun.