CONSTRUCTION PROGRESS OF THE HYGGE LUX – NOVEMBER 2023

December 2023
02

In November 2023:

  • Section IV:
    • Work was carried out on the installation of facade insulation.

 

  • Section IV:
    • The columns of the 1st floor of commerce are 100% filled;
    • Work is underway to arrange the ceiling of the 1st floor of commerce.

 

  • Section V:
    • The columns of the 4th floor are fully arranged;
    • The ceiling of the 4th floor is 100% filled
    • The columns of the 5th floor are fully arranged;
    • 100% coverage of the 5th floor.

 

  • Section VI:
    • The ceiling of the 6th floor is 100% filled;
    • The columns of the 7th floor are fully arranged;
    • The overlap of the 7th is filled with 100%;
    • Bricklaying of the walls of the 1st residential floor has begun.
/