In September 2022:
- More than half of the cladding with metal sheets of the roof of the I section has been completed;
- The installation of the wooden structures of the roof of the II section has been completed;
- The installation of the wooden structures of the roof of the II section has begun;
- Masonry of the partitions of the 3rd and 5th floors of the II section has been completed;
- Masonry of the walls, ventilation ducts and chimneys of the 6th floor of the III section has been completed;
- Installation of ventilation and chimney units on the 5th and 6th floors of the III section was completed;
- Masonry of the partitions of the 5th floor of the III section has begun;
- Masonry of the parapets and walls of the 6th floor of the IV section has begun;
- Masonry of the partitions of the 1st, 2nd, and 5th floors of the IV section has begun;
- The installation of the ventilation units of the 1st, 2nd and 3rd floors of the IV section has begun;
- External networks have been arranged (wells have been installed and pipes have been laid under drains) of the IV section;