In October 2022:
- The installation of aluminum window structures in sections I and III has been completed;
- The installation of roofs over the chimneys in the I section has been completed;
- Installation of the water supply and heating system continued on the 7th floor of the III section;
- Installation of cement-sand screed in sections I and III has begun;
- Finished installation of window moldings in the III section.