As of June 2024:
- Section IV:
- The installation of individual heating boilers has been completed.
- Section IV:
- The brickwork of the walls of the 5th residential floor is 50% complete;
- Partitions of the 2nd residential floor are 50% completed;
- Partitions of the 3rd residential floor are 50% completed;
- Partitions of the 4th residential floor are 50% completed;
- The partitions of the 5th residential floor are 50% complete.
- Section V:
- Installation of the PVC membrane on the roof is completed;
- Sewer risers are being installed.
- Section VI:
- Sewer risers are being installed.