Хід будівництва ЖК HYGGE lux - CONSTRUCTION PROGRESS OF THE HYGGE LUX – JUNE 2023 - LEV Development (Лев Девелопмент)

CONSTRUCTION PROGRESS OF THE HYGGE LUX – JUNE 2023

June 2024
11

As of June 2024:

  • Section IV:
    • The installation of individual heating boilers has been completed.

 

  • Section IV:
    • The brickwork of the walls of the 5th residential floor is 50% complete;
    • Partitions of the 2nd residential floor are 50% completed;
    • Partitions of the 3rd residential floor are 50% completed;
    • Partitions of the 4th residential floor are 50% completed;
    • The partitions of the 5th residential floor are 50% complete.

 

  • Section V:
    • Installation of the PVC membrane on the roof is completed;
    • Sewer risers are being installed.

 

  • Section VI:
    • Sewer risers are being installed.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT