As of June 2024:
- In the I section:
- The work on plastering the corridors and staircase has been completed;
- Baskets for air conditioners have been installed on the facade.
- In the II section:
- Corridors and staircases on floors 2-5 were plastered;
- Electricity metering cabinets were installed in the corridors;
- Work has begun on the installation of railings on the balconies.
- In the III section:
- Corridor plastering work has begun;
- Electricity metering cabinets were installed in the corridors;
- Work has begun on the installation of railings on the balconies;
- Baskets for air conditioners have been installed on the facade.
- In the IV section:
- Electricity metering cabinets were installed in the corridors;
- Installation of baskets for air conditioners is in progress;
- Work has begun on the improvement of the adjacent territory.
- In the V section:
- In the process of arranging the facade;
- Plastering works are being carried out;
- Elevators have been installed.
- In the VI section:
- The first layer of the roof is completed;
- Construction of the facade has begun;
- Installation of window structures has been completed.
- In Section VII:
- Monolithic works are completed;
- Masonry of the 3rd floor is in progress;
- Ventilation ducts have been installed on the 1st-3rd floors.
- In Section VIII:
- We reinforce the last floor slab (above the 7th floor);
- Bricklaying of the 3rd floor continues;
- Ventilation ducts have been installed on the 1st-3rd floors.
- In Section IX:
- The installation of plumbing networks in apartments has been completed;
- Installation of electrical networks is underway;
- Furnishing of the facade is in progress.