SILENT PARK CONSTRUCTION PROGRESS - JUNE 2023[:] - LEV Development (Лев Девелопмент)

SILENT PARK CONSTRUCTION PROGRESS – JUNE 2023

June 2024
12

As of June 2024:

House 1:

  • Finished puttying works;
  • The waterproofing of the terraces has begun;
  • Landscaping works continue around, as well as between the 1st and 2nd buildings;
  • 95% of the work on the arrangement of the automatic irrigation system and the lighting system has been completed.

House 2:

  • Plastering works have started;
  • Finished plasterboard works;
  • The terraces were waterproofed.

House 3:

  • Plasterboard works have started;
  • The laying of tiles in the entrances has begun;
  • The waterproofing of the yard between the 2nd and 3rd houses has been completed;
  • The preparatory works for landscaping between the 2nd and 3rd building have been completed.

House 4:

  • Installation of heating and water supply systems in apartments is being carried out;
  • We install elevators;
  • Finished plastering works;
  • Facade works are being carried out.

House 5:

  • Windows are being installed;
  • Facade works are being carried out;
  • We install elevators;
  • The first layer of roofing material was installed on the roof of the house;
  • Internet cables are being installed.

House 6:

  • Masonry work on external walls and partitions on the 1st, 2nd and 3rd floors is actively ongoing;
  • The vertical elements of the 5th floor were concreted.
/