As of June 2024:
House 1:
- Finished puttying works;
- The waterproofing of the terraces has begun;
- Landscaping works continue around, as well as between the 1st and 2nd buildings;
- 95% of the work on the arrangement of the automatic irrigation system and the lighting system has been completed.
House 2:
- Plastering works have started;
- Finished plasterboard works;
- The terraces were waterproofed.
House 3:
- Plasterboard works have started;
- The laying of tiles in the entrances has begun;
- The waterproofing of the yard between the 2nd and 3rd houses has been completed;
- The preparatory works for landscaping between the 2nd and 3rd building have been completed.
House 4:
- Installation of heating and water supply systems in apartments is being carried out;
- We install elevators;
- Finished plastering works;
- Facade works are being carried out.
House 5:
- Windows are being installed;
- Facade works are being carried out;
- We install elevators;
- The first layer of roofing material was installed on the roof of the house;
- Internet cables are being installed.
House 6:
- Masonry work on external walls and partitions on the 1st, 2nd and 3rd floors is actively ongoing;
- The vertical elements of the 5th floor were concreted.