CONSTRUCTION PROGRESS OF THE HYGGE LUX – April 2025

April 2025
15

As of April 2025:

Section 4:

  • Elevator installation completed;
  • Balcony railings are being installed;
  • The installation of ceramic tiles on the ventilated facade is being completed;
  • A pumping station has been installed in the house.

Section 5:

  • Plastering of the walls in the entrance hall has begun;
  • Installation of balcony railings has begun.

Section 6:

  • Installation of entrance doors in apartments has begun;
  • Electrical metering cabinets have been installed;
  • Gas meters are installed;
  • The walls in the entrance are being primed for painting.

In general, around the house:

  • Work on improving the territory is ongoing;
  • Facade work has been completed.
/