As of April 2025:
Section 5:
- Railings have been installed on the stairwells;
- The patio enclosure on the courtyard side has been completed;
- Painting work has begun in the 2nd entrance.
Sections 6–7:
- Patio fencing is being installed from the courtyard side;
- Installation of roofs over ventilation ducts is underway;
- Improvements are underway in the courtyard.
Section 8:
- Patio fencing is being installed from the courtyard side;
- Installation of roofs over ventilation ducts is underway;
- Improvements are underway in the courtyard;
- An elevator has been installed;
- The facade is being installed.
Section 9:
- The patio enclosure on the courtyard side has been completed;
- Plastering work is 70% complete.