PERFECT LIFE CONSTRUCTION PROGRESS - April 2025[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – April 2025

April 2025
16

As of April 2025:

Section 5:

  • Railings have been installed on the stairwells;
  • The patio enclosure on the courtyard side has been completed;
  • Painting work has begun in the 2nd entrance.

Sections 6–7:

  • Patio fencing is being installed from the courtyard side;
  • Installation of roofs over ventilation ducts is underway;
  • Improvements are underway in the courtyard.

Section 8:

  • Patio fencing is being installed from the courtyard side;
  • Installation of roofs over ventilation ducts is underway;
  • Improvements are underway in the courtyard;
  • An elevator has been installed;
  • The facade is being installed.

Section 9:

  • The patio enclosure on the courtyard side has been completed;
  • Plastering work is 70% complete.
/
Residential Complex
Number of rooms
1 2 3 4 5 6 7
Square, m2
Price, UAH / m2
Floor
More options
SELECT APARTMENT