As of July 2024:
- Section IV:
- The brickwork of the walls and partitions of the residential floors has been completed;
- The brickwork of commercial premises is 50% ready;
- Installation of sewer and drainage risers is 100% ready.
- Section V:
- The brickwork of commercial premises is 50% ready;
- Installation of sewer and drainage risers is 100% ready.
- Section VI:
- Installation of sewer and drainage risers is 100% ready.