As of July 2024:
- In the I section:
- Corridors and staircases of floors 2-7 are being painted.
- In the II section:
- All doors to the apartments have been installed;
- Completed plastering of corridors and staircase;
- Work on the installation of railings on the balconies is underway.
- In the III section:
- All doors to the apartments have been installed;
- Corridors and staircases of floors 2-5 are puttyed;
- Work on the installation of railings on the balconies is underway.
- In the IV section:
- Corridors and staircases of 2-4 floors are being puttyed;
- Works on the improvement of the territory of the house are being carried out.
- In the V section:
- Facade work is 80% completed;
- Plastering in the 1st entrance has been completed.
- In the VI section:
- Construction of the facade is in progress.
- In Section VII:
- Masonry of the external walls and partitions of the 3rd floor has been completed;
- The masonry of the 4th floor is in progress.
- In Section VIII:
- Monolithic works have been completed;
- Masonry of the external walls and partitions of the 3rd floor has been completed;
- The masonry of the 4th floor is in progress.
- In Section IX:
- Electric networks to the apartments and to the MZK have been installed;
- Construction of the facade is in progress.