PERFECT LIFE CONSTRUCTION PROGRESS - JULY 2023[:] - LEV Development (Лев Девелопмент)

PERFECT LIFE CONSTRUCTION PROGRESS – JULY 2023

July 2024
24

As of July 2024:

  • In the I section:
    • Corridors and staircases of floors 2-7 are being painted.

 

  • In the II section:
    • All doors to the apartments have been installed;
    • Completed plastering of corridors and staircase;
    • Work on the installation of railings on the balconies is underway.

 

  • In the III section:
    • All doors to the apartments have been installed;
    • Corridors and staircases of floors 2-5 are puttyed;
    • Work on the installation of railings on the balconies is underway.

 

  • In the IV section:
    • Corridors and staircases of 2-4 floors are being puttyed;
    • Works on the improvement of the territory of the house are being carried out.

 

  • In the V section:
    • Facade work is 80% completed;
    • Plastering in the 1st entrance has been completed.

 

  • In the VI section:
    • Construction of the facade is in progress.

 

  • In Section VII:
    • Masonry of the external walls and partitions of the 3rd floor has been completed;
    • The masonry of the 4th floor is in progress.

 

  • In Section VIII:
    • Monolithic works have been completed;
    • Masonry of the external walls and partitions of the 3rd floor has been completed;
    • The masonry of the 4th floor is in progress.

 

  • In Section IX:
    • Electric networks to the apartments and to the MZK have been installed;
    • Construction of the facade is in progress.
/