In August 2023:
- Section IV:
- Completed plastering of common corridors and staircases.
- Section IV:
- Pile drilling is completed.
- Section V:
- The covering of the 1st floor has been completed;
- The arrangement of the walls of the 2nd floor has been completed;
- Installation of piles, grids and foundation slab is completed;
- Section VI:
- The ceiling of the 3rd floor has been completed;
- The arrangement of the walls of the 4th floor has been completed;
- The roofing of the 4th floor has been completed.