Construction progress of FEEL HOUSE – AUGUST 2023

August 2023
25

Actual news for August from the FEEL HOUSE residential complex construction site in Lviv:

In the I section:

  • Installation of gas pipes in apartments is completed.

In II-III sections:

  • Painting works have begun;
  • Installation of gas pipes in apartments is completed.

In the IV section:

  • Water meters have been installed.

 

Overall for the house:

  • Monolithic works on the arrangement of the attached parking lot are in progress.
/